Main Library Gets Much Needed Overhaul
As you may have heard on local news, the City is in litigation with the original contractor for the new Main Library. The law suit is for approximately $1.4 million in damages to the Main Library due to construction shortfalls when Main was constructed, 2003-2005.
In the fall of
2013, City Of Jacksonville Public Works (COJ/PW) began an invasive assessment
to determine the cause and pin-point the source of damages within the Main
Library believed to be due to faulty construction. During this
assessment, it was found that there was delamination of stucco (separation of
exterior stucco from the wall of the building), H20 intrusion linked to
installation shortfalls of exterior windows and skylights, along with H2O
intrusion identified within the courtyard.
Long story
short, ACON Construction was contracted by COJ/PW to conduct this activity
on/about October 2013. Work is still in process to rectify the damages
and it is anticipated to be completed by October 2015.
Kudos to employees
who have been patient with the necessary noise and open areas on cold days
while windows were removed and reinstalled.
Thanks to CR&M’s Marsha Blasco for
the photo of the installation of new windows at the Main Library.